below is the latest update to help you stay informed about the construction activities and road closures. keep an eye on this update for important information on detours and traffic changes.
.jpg)
N. Harwood Closure through August 30th
july 31, 2026
N. Harwood Street will be closed through Saturday, August 30th, in both directions from Woodall Rodgers to the north side of our project site. This closure is necessary to allow for crane operations to install precast panels. The 2000 McKinney Avenue garage and the 1920 McKinney Avenue garage and loading dock will remain accessible from McKinney Avenue as per the traffic plans below.
Parkside Construction Traffic Plan

In addition, Atmos has notified us they will begin construction of a new gas line south along Harwood. Below are the details regarding their schedule and traffic plans.
Atmos Tentative Schedule:
-
Harwood Street & McKinney Avenue Intersection for the crossing
-
Scheduled Start: August 3, 2026
-
Scheduled Completion: August 14, 2026
-
Duration: 2 weeks
-
-
Harwood Street
-
Scheduled Start: August 17, 2026
-
Scheduled Completion: August 28, 2026
-
Duration: 2 weeks
-
Atmos Traffic Plans